Over Rs 1 billion loss on purchase of coal, COPE reveals
Posted on October 7th, 2020

Courtesy Adaderana

It was revealed at the Committee on Public Enterprises (COPE) held yesterday (06) that a loss of Rs. 1.1 billion has been incurred as a result of not specifying the quantity of coal required when calling for tenders for the purchase of coal by the Ceylon Coal Company (Pvt) Limited.

It was also revealed that the Ceylon Coal Company (Pvt) Limited had purchased coal under the short-term method, without following the proper procurement process.

This was revealed at the first meeting of the Committee on Public Enterprises (COPE) held in Parliament convening a group of senior officials of the Ceylon Coal Company Limited to inquire into the procurements made by the Coal Company.

The committee was convened under the patronage of its chairman Member of Parliament Prof. Charitha Herath and Minister Mahinda Amaraweera, Minister Mahindananda Aluthgamage, State Minister Nalaka Godahewa, State Minister Sarath Weerasekera, State Minister Ajith Nivard Cabraal, Members of Parliament Patali Champika Ranawaka , Eran Wickramaratne, Jagath Pushpakumara, Premnath C. Dolawatta, S. M. Marikkar and Rauf Hakeem were  present at the meeting.

The officials told the committee that they expected to take the advantage of the fluctuations in market prices by purchasing coal under the short-term method rather than the long-term method. However, the Chairman of the Committee on Public Enterprises further pointed out the need to implement these tenders with the approval of the Cabinet of Ministers in accordance with the prescribed procurement process.

It was revealed at the COPE that the Norochcholai Lakvijaya Power Plant was added to the national grid to meet a 900 MW electricity requirement, but there was a shortfall of 90 MW. It was further revealed at the COPE meeting that only 810 MW is actually being generated and that 90 MW of vacuum is an unavoidable electricity requirement.

It has been revealed that the Secretary of the Cabinet Procurement Committee has been absent from the Procurement Committee on eight occasions and an Additional Secretary has been appointed for this purpose. Therefore, the COPE Committee noted that there is a problem with the legitimacy of decisions taken. However, officials said that it was possible to appoint an additional secretary for this purpose. The Chairman recommended to submit an immediate report to the COPE to ascertain whether this was correct.

The committee questioned the reasons for handing over three barges purchased by the Ceylon Electricity Board at a cost of Rs. 1100 million to the Sri Lanka Navy. The Committee directed the Secretary to the Ministry to submit an immediate report on the methodology of handing over the barges to the Sri Lanka Navy and the reasons for their inability to maintain them.

Although it was stated in the newspaper advertisements that 5 years’ experience in coal supply is required, the matter of issuing applications to companies with 3 years’ experience was also discussed at this meeting. The committee was of the view that this had put the coal company at a disadvantage. The committee also discussed that there was no formal procedure for the last day of bidding. The Committee decided that these matters should be duly investigated.

The Committee also considered whether the involvement of the Sri Lanka Shipping Corporation in the purchase of coal would result in a loss than the purchase of coal through another institution under the normal tender system. The Committee also recommended to submit a report in this regard to the Committee on Public Enterprises as soon as possible.

The committee also noted the need for regular meetings with the Ceylon Electricity Board, the Ceylon Shipping Corporation, the Ceylon Coal Company and the relevant ministry and COPE members also drew attention to the cost of diesel power plants and coal power plants.

The COPE Chairman finally recommended to submit all reports on these matters to the COPE within a month.

2 Responses to “Over Rs 1 billion loss on purchase of coal, COPE reveals”

  1. aloy Says:

    These things no longer are interesting topics. The citizens know that ‘naduth hamuduwange, baduth hamuduwange’ and there is nothing they can do about it under the circumstances. They are struggling to live for the day. Perhaps same in America too. Their coffers are also empty. Hence Trumps reluctance to release $ 2.2 Trillion as Covid assistance to his citizens. We too should plan for the day by concentrating on production of food items; the Viyaththu can take a rest, I suppose. Nobody is sure how long this situation is going to last.

  2. aloy Says:

    While the poor farmers (and house maids in ME) do their duty to maintain the country the GOSL should try to appoint young persons of integrity from among the Sinhalese to important positions. The others may do the job temporarily well but work towards their own interest at the end. The Brandix affair is just one case in point.

Leave a Reply

You must be logged in to post a comment.

 

 


Copyright © 2024 LankaWeb.com. All Rights Reserved. Powered by Wordpress