Can the CEB’s attempt to curtail solar power generation be justified?
Posted on May 30th, 2025
Courtesy Daily Mirror

However, when this newspaper contacted Eng. Hedigallage to find out about the US$ 1 million payment to RMA Energy for the consultancy service provided for this project, and also to know how Dr. Siyambalapitiya could change his stance regarding RE addition to the grid after assuming duties as Chairman CEB, the former accused this newspaper of slinging mud at him
All these unacceptable explanations are given perhaps for two reasons. The first could be to conceal their inability to manage the system and the second reason is because a group of CEB officials connected to the diesel mafia are heavily losing their ‘income’ when electricity is generated from solar
When purchasing solar power, we- the CEB — pay them with rupees whereas we have to pay in dollars when purchasing coal or diesel power to procure the fuel. Just because this group of CEB Engineers are receiving commissions from this coal and diesel generation, but not a cent from solar generation, they opt to purchase power generated from coal and diesel,” sources said
By Nirmala Kannangara
Startling revelations have come to the fore as to how the present administration of the Ceylon Electricity Board (CEB) is attempting to promote thermal and coal power by curtailing renewable power generation.
For the first time in the history the CEB, it has switched off all rooftop solar plantsa over 100kW and instructed all rooftop and ground mounted solar system owners to switch off their inverters voluntarily to ensure the reliable and stable operation of the national grid during recent New Year season. The CEB claimed that this decision was taken due to the significantly low demand observed in the system.
However, most of the roof top solar owners disregarded this unusual directives. It is now reported how the CEB Engineers have forcibly entered ground mounted solar farms in many parts of the country during the festive season and switched off their inverters from 9am to 4pm for five consecutive days.
Giving various unacceptable explanations as to why Renewable Energy (RE) has to be curtailed, the CEB maintains that this curtailment was facilitated to maintain an adequate level of dispatchable generation and improve sufficient system inertia.
All these unacceptable explanations are given perhaps for two reasons. The first could be to conceal their inability to manage the system and the second reason is because a group of CEB officials connected to the diesel mafia are heavily losing their ‘income’ when electricity is generated from solar. When coal and thermal generations are minimised, these vested parties do not get their ‘commission’ as solar generation does not benefit them although it benefits the country. This is the first time orders were given to switch off not only roof top solar inverters, but also ground mounted solar as well,” a highly reliable source from the Sustainable Energy Authority told this newspaper.
Development Master Action Plan
Sri Lanka Sustainable Energy Authority (SLSEA) and the CEB drafted the ‘Renewable Energy Development Master Action Plan (REDMAP) 2023/ 2026’ in 2022 highlighting the importance in adding renewable energy (RE) to the national grid, especially from wind and solar. This was part of the Long-Term Generation Plan (LTGEP) that was drafted in line with the government’s policy to target achieving 70% RE by 2030, and to ensure timely implementation of RE additions to the system. CEB’s decision to ignore the instruction given in these reports and purchasing diesel and coal at a higher cost has raised eyebrows amongst their own engineers.
When purchasing solar power, we- the CEB — pay them with rupees whereas we have to pay in dollars when purchasing coal or diesel power to procure the fuel. Just because this group of CEB Engineers are receiving commissions from this coal and diesel generation, but not a cent from solar generation, they opt to purchase power generated from coal and diesel,” sources said.

As per the REDMAP, the proposed plan was to generate 1,795MW solar and 575 MW wind and other RE from 2023 to 2026. Having issued a report as such, what was the reason for the CEB to curtail RE and go ahead with costly thermal and coal power?
When drafting the REDMAP, Consultancy service to the Asian Development Bank (ADB) was provided by the Resource Management Associates (Pvt) Ltd (RMA) which is also known as RMA Energy, which was headed by the present Chairman of CEB Dr. Thilak Siyambalapitiya until September 2024 and presently by his wife.
RMA Energy provides consultancy services to ADB and World Bank (WB) on the country’s power sector. Having recommended to add more RE generation to the national grid at the time the report was drafted, this decision was ignored once he became CEB chairman and he wanted to purchase costly coal and thermal power by curtailing RE generation. It was even alleged that he was attempting to tender rooftop solar and ground mounted solar which is less than 10 MW for an unknown reason,” the Sustainable Energy Authority source told on condition of anonymity.
As per the CEB and Public Utilities Commission of Sri Lanka (PUCSL) official data, from the time the REDMAP was issued and up to now only 793 MW Solar plants have been commissioned, a figure which includes rooftop solar units.
US$ 1 million paid
According to sources, it was the ADB that gave the grant to prepare this report ‘Way Forward of Integration of Renewable Energy Resources to the National Grid from 2023 to 2026 by Means of Appropriate Business Models’. Director General Power Sector Reform Secretariat and member of the Energy Committee, Eng. Pubudu Niroshan Hedigallage, has made a status most on his Face Book account, adding that US$ 1 million has been paid to RMA Energy for the consultancy services provided.
However, when this newspaper contacted Eng. Hedigallage to find out about the US$ 1 million payment to RMA Energy for the consultancy service provided for this project, and also to know how Dr. Siyambalapitiya could change his stance regarding RE addition to the grid after assuming duties as Chairman CEB, the former accused this newspaper of slinging mud at him.
I know who is behind this mud slinging campaign. You can write anything you want, but I am not scared of mud slinging,” Eng. Hedigallage said.
Meanwhile questions have been raised as to how Dr. Siyambalapitiya’s wife Namalee Siyambalapitiya continued to work for RMA Energy in the capacity of director even after the former had resigned from his post to accept CEB Chairmanship.
RMA earns hundreds of thousands of Dollars from these consultancies annually related to Sri Lankan power sector. What sought of conflict-of-interest policy has he adopted before he took over office at CEB? Has he divested of his interest in RMA Energy? Has his wife divested of her interest in RMA Energy? Have they resigned from all operations of RMA Energy and handed over the RMA Energy Management and technical control of the company? Since RMA is currently consultants to Offshore Wind Power on pre-feasibility assessment, have they recused themselves from this engagement or any project related to the country’s power sector? Is Tharaka Siyambalapitiya who is the senior project engineer of this company an offspring or a relative of the CEB Chairman?
Conflict of interest
Though the NPP government that assumed power promised to put a complete stop to all frauds, it has not lived up to its promises and appointed Dr. Siyambalapitiya to the CEB with such conflict of interest in place at CEB – the den of corruption,” sources alleged.
Questions have been further raised whether the decision to curtail solar power generation was due to ‘the rapid’ increase in rooftop and ground mounted solar and other inverter base Non-Conventional Renewable Energy (NCRE) plant installation which has resulted in substantial frequency fluctuations owing to low system inertia which becomes critical during disturbances leading to the frequent activation of the Under Frequency Load Shedding (UFLS) scheme and increasing the risk of tripping major thermal power plants? The SLSEA has said that the CEB should reveal to the consumers as to why frequency fluctuation is reported now and never before.
They claim that after the country’s economic recession, the demand for electricity has gone down steadily while rooftop and ground mounted solar parks have come up in numbers and these additions to the national grid is the cause for the frequency fluctuation. Before Dr. Siyambalapitiya took office there were no concerns for the safety and stability of the national grid, but it’s only now that they talk about a risk of tripping major thermal and coal power plants. Why is this?” sources alleged.
Deputy General Manager (System Control) CEB, Eng. M.B.S. Samarasekara by letter dated November 12, 2024, to AGM (Transmission Non-Wired Operation) has informed that immediate mitigatory actions must be taken to improve system demand and system stability during weekends and holidays with high NCRE penetration to the system.
***This letter ***further states, ‘This is to bring to your attention a matter of significant importance regarding the stability and reliability of the Sri Lankan power system, especially considering the rapid increase in rooftop solar plant installations and other inverter base NCRE plants.
‘The rapid increase in rooftop solar installations has introduced significant irregularities to the operations of the power system. This issue is particularly severe during long holidays, especially on sunny Sundays when industrial and commercial demands are exceptionally low. On these days, many dispatchable plants are not dispatched to accommodate the must run NCRE generation, resulting in substantial frequency fluctuations due to low system inertia. This problem becomes critical during disturbances, leading to the frequent activation of the UFLS scheme and increasing the risk of tripping major thermal power plants, particularly the Lakvijaya power plant.
‘On September 22, 2024, the system’s minimum demand of 670 MW occurred around 10.53hrs. During this period system operators observed significant fluctuations in system frequency, even the machine loads were adjusted. Consequently, it was necessary to curtail available NCRE (inverter based) generation to avoid further demand reduction and improve system inertia by adding more generation plants. The lowest recorded demand in 2024 at 670 MW prompted the curtailment of approximately 160 MW of NCRE between 10 and 15.00hrs to prevent system demand from dropping further to 600 MW. This curtailment has facilitated to maintain and adequate system inertia. Following the curtailment system demand increased to 820 MW, allowing for the dispatch of higher inertia plants in order to enhance system stability and resilience.
‘It is noted that the system frequency is experiencing rapid fluctuations and instability especially during daytime when the demand is exceptionally low. This instability is alarming and indicates the need for immediate mitigative actions, such as the incorporation of fast frequency arresting solutions into the system as soon as possible.
‘It is noted that during extremely low demand periods with the increasing of non-dispatchable renewable energy sources have compelled the National System Control Center (NSCC) to shut down more dispatchable plants, resulting in a significant reduction in system inertia. This loss of inertia substantially increases the risk of a total system collapse in the event of any system faults or disturbances.
‘Given these challenges, it is unlikely that the system can maintain resilience during such incidents.
‘As an immediate step to mitigate low demand risks, it is suggested to introduce new tariff rates of the industrial category on weekends and special holidays could encourage increased electricity usage on these low demand period until the proposed power system ancillary services are in place. By offering incentivised rates industries would be motivated to shift more operations to these days to help improve system demand and enhance the grid stability and resilience.
‘The investigation into operating large hydro power plants such as Victoria, Kothmale, Samanalawewa, Uma Oya and New Lakshapana in synchronous condenser mode reveals a promising opportunity to enhance grid stability and reactive power support. With the recent installation of Automatic Voltage Regulators these plants have the potential to operate effectively in this mode. Notably, New Lakshapana has the necessary infrastructure for synchronous condenser operation established during its refurbishment, though this capacity has yet to be fully utilised. Implementing this mode across these hydro plants could significantly strengthen grid stability by providing crucial reactive power without generating active power.
‘Evaluating the feasibility of operating Gas Turbine Generator 7 (GT 7) in synchronous condenser mode presents a promising opportunity to enhance system inertia and stability. As GT 7 has the highest inertia constant (H constant) in the Kelanitissa thermal fleet, operating it in this mode would allow it to provide essential reactive power and stabilise frequency fluctuations without generating active power. This approach could lead to a notable improvement in system resilience and ultimately strengthening overall grid stability under varying demand and supply conditions.
‘It is imperative to prioritise the installation of fast frequency reserves and energy storage systems such as battery energy storage systems (BESS), fast acting Gas Turbines, Flywheel Energy Storage Systems etc. These systems can provide the necessary rapid response to frequency deviations, thereby enhancing the stability and reliability of the power system.
‘These recurring low demand periods (especially holidays with good sunny and windy environment) highlight the critical necessity for an NCRE control desk with forecasting and monitoring facility at the National System Control Center and respective Distribution Control in order to effectively ensure grid security within permissible limits. Therefore, the implementation of an NCRE control desk should be given priority.
‘The spinning reserve requirement has to be reviewed accordingly when more NCRE is added, as a hot spinning reserve of 5% may not be satisfactory to maintain the system stability and reliability in future.
‘In future major generation contributions will be generated from NCRE sources and may require curtailments. Therefore, a proper mechanism for curtailments has to be formulated for future NCRE additions (at least for above 5MW scale).
‘Additionally, it is advisable to evaluate the minimum operating power and ramp rates for both hydro power plants and the CEB thermal power plants. This assessment will ensure sufficient capacity to accommodate additional power plants within the system, resulting in a significant improvement in system inertia.
‘Accordingly, please make immediate arrangements to effectively tackle these challenges and ensure resilient operation even during power system disturbances. This requires the timely commissioning of fast frequency response sources and the outline of alternative methods such as a new tariff category for low demand periods and the operation of existing plants in synchronous condenser mode where feasible. These measures will help stabilise the grid and improve system resilience’.
Stability and reliability
Although Eng. Samarasekera’s said letter has recommended to take certain steps claiming their ‘significant importance regarding the stability and reliability of the country’s power system’, the suggested decisions should have been implemented by the CEB before this situation occurred.
Their deliberate failure cannot penalise either the consumers or investors. The prevailing least cost long term generation expansion plan approved by the PUCSL contains 20MW/50Mwh battery storage in 2024, 100MW/400MWh batter storage in 2025 and a further100MW/400MWh battery storage in 2026. CEB has not taken any action to have these storage facilities in place and now recommending having battery storage facilities. The consumers and investors should question the CEB why the energy storage systems and synchronous machine in the generation plan was not implemented by CEB,” sources added.
Even though Eng. Samarasekara has proposed many ways to face this challenge in his letter, the management has selected switching off existing Solar and curtailing the future expansion of Solar catering to the requirement of Thermal Mafia citing various technical reasons, it is learnt.
When we contacted Eng. Samarasekera to find out why the CEB is interested in promoting thermal and coal generation and why he has requested to formulate a proper mechanism to curtail for future NCRE additions, Samarasekera wanted this newspaper to get the information from CEB Spokesman Eng. Dhammika Wimalaratne.
When Eng. Wimalaratne was contacted regarding this matter he said that the CEB had requested all rooftop solar system operators to switch off their inverters from April 12 to April 21, with the utmost concern for the safety and stability of the national grid.
With the country being bankrupt and the economy shrunk, factories were closed down and the demand for electricity dropped significantly. However, in the meantime, due to low interest bank loans given for solar installations, the number of rooftop and ground mounted solar parks came up rapidly. As a result, solar power generation went up speedily and due to low demand, CEB had to shut down coal and thermal plants to balance the situation. The larger power plants provide a critical service to the grid called ‘inertia’, which helps keep the electricity frequency stable though solar or RE cannot provide such an assurance to the grid. Without adequate inertia, even a small problem can cause frequency problems, leading to partial or total blackouts. The demand on the national grid was reduced to as low as 1550 MW in the morning hours during the festive season. As a result, a surge in solar generation forced CEB to shut down large synchronous generators—such as hydro, and thermal plants—which are crucial for grid stability.
When asked whether the CEB and the Sustainable Energy Authority didn’t know what the future consequences would be, when drafting the LTGEP and REDMAP that planned 2, 728 MW renewable energy plants by 2026, Eng. Wimalaratne said that it should be asked from those who drafted these reports and that he cannot give a proper answer to it.
This is a good question, but it should be posed to those who drafted the reports. Without having battery energy storage system there is no way we can store the solar generated power. As the country faced the financial crisis, many factories and businesses were closed down and the electricity demand came down whereas the generation picked up after the banks gave low interest loans to install solar panels. Last December we got a loan from the ADB to set up 100 MW battery energy storage system. We hope that we will not have to curtail solar generation once this system is implemented,” he said.
According to him, only rooftop solar inverter owners were asked to switch off but not the ground mounted solar inverters.
Solar parks interfered with
Although Eng. Wimalaratne said so, several ground mounted solar companies on condition of strict condition of anonymity told this newspaper that CEB Engineers entered their solar parks forcibly during the festive season and switched off their inverters which has caused huge losses to their businesses.
We invested several billions of rupees for these projects. But due to the CEB’s arbitrary decision we lost around Rs.200, 000 per day. Who is going to compensate for this loss?” asked representatives of ground mounted solar companies.
According to Eng. Wimalaratne, until battery energy storage systems are installed, the national grid has to rely on large synchronous machines to supply inertia and ensure stability.
CEB Engineers have forcibly entered ground mounted solar farms during the festive season and switched off inverters
At present, Sri Lanka does not have this facility nor advanced solar inverters that can provide this support. Sri Lanka has over seven million electricity consumers, but a mere 100,000 have installed rooftop solar panels. When the grid becomes unstable, everyone has to pay the price,” he added.
Although Eng. Wimalaratne said that larger power plants provide a critical service to the grid to keep the electricity frequency stable though solar or RE cannot provide such an assurance, questions are raised why the Ministry of Energy is conducting pre-feasibility assessment stakeholder workshop to develop Offshore Wind Power potential in the country.
By letter dated March 5, 2025, Additional Secretary (Development and Procurement), Ministry of Energy, T. Prassanth has sent a letter to the Director General Sri Lanka Sustainable Energy Authority inviting them to attend a workshop for the said workshop.
***The letter states, ‘The Ministry of Power and Energy along with the Sri Lanka Sustainable Energy Authority implemented technical assistance from the World Bank to conduct studies towards developing offshore wind power potential in Sri Lanka.
‘The study was conducted by Pondera Consult, an experienced international offshore wind consultancy based in the Netherlands in collaborating with their national counterpart, RMA Energy.
We are pleased to inform you that, as communicated, a follow-up workshop is organised to present the pre-feasibility findings.****
CEB maintains that this curtailment was facilitated to maintain an adequate level of dispatchable generation and improve sufficient system inertia
When contacted, Additional Secretary (Development and Procurement), Ministry of Energy, T. Prassanth, to find out how much RMA Energy were paid to this project, the former said that she doesn’t know as this workshop was started few months ago.
This is not a loan, but a grant from the World Bank. So, we do not know how much this consultancy firm was paid as their fee is paid straight to that company but not through the government or the Ministry,” she said.
When met Chairman Dr. Thilak Siyambalapitiya in his office to find out how much the electricity consumers have to pay for the whims of the thermal and coal interested CEB Engineers though he and his company-RMA Energy when providing consultancy services when drafting the REDMAP and for the ongoing offshore wind power feasibility assessment project, the proposal to add more RE to the grid by 2030, he said that after the country faced an adverse economic situation, the power demand came down rapidly but the RE addition increased.
‘I explained you in detail how a power system is planned and operated to ensure stability and economic operation and how the share of renewable energy in the grid has grown from a minimum of 29% in 2012 to 55% in 2024. This growth did not happen by accident, but through efforts of all: governments, SLSEA, CEB, LECO and RE investors.
‘Long-term generation expansion plan of CEB 2023, approved by PUCSL was based on the demand forecast which says ‘demand has to be 18,725 GWh in 2025’. However, we will cross 16,000 GWh this year. Peak forecast will be 3283 MW; but we will not even cross 2800 MW this year. The conclusion is that the demand is not growing as expected. For 2024, PUCSL approved 160 MW of rooftop solar but we have facilitated 650 MW of new solar, this mean the supply is growing but customer demand is not growing. By January 2024, there should have been 20 MW and by January 2025, 100 MW of battery storage. None of them are available. They should have been procured to purchase these batteries in 2023 and 2024 respectively but procurement process was started only recently. The previous management was grappling with the economic crisis, I do not blame anyone for that delay.
Surplus of generation
‘So, until the demand grows plus storage is established, especially on holidays, all types of power plants have to be cut back. Electricity thus has to be produced at the same time the customer wants it. When there is a surplus of generation, we first cut off all our oil burning power plants, which are very expensive which is more than Rs 35 per unit. Hydropower generation is then curtailed but it is limited by drinking water and irrigation requirements downstream, determined by the Water Board and Mahaweli Authority. Then we curtail CEB’s own renewable energy power plants- Mannar wind power 100 MW and the smaller hydropower plants at Nilambe, Uda Walawe and Inginiyagala. Then if the supply is still in excess, we curtail the coal power plant which purchase price is Rs 19 per unit in order to absorb solar power (price ranges from Rs 15.50 to 42, depending on which year, and which type of contract you signed).
If you log on to CEB website you can see how CEB power plants of all sorts are curtailed on any day, to absorb renewable energy.
‘Like any other similar power plants worldwide, the coal power plant has a special feature. It cannot be cut back to very low levels of production as it has to be switched off completely. If switched off during daytime there will be a delay and an additional cost to restart because it is required to meet the customer demand in the night. Yet in the run-up to the New Year holidays, CEB switched off one coal generator completely, and cut back the other 2 to the minimum during daytime to maximise absorbing solar power and then ramped up at nightfall.
‘Renewable energy is curtailed only as a last resort. The very low demand during New Year holidays was anticipated. It became acute this year, owing to large solar capacity installed in 2024, against a demand that is not growing. So 2025 holidays were different to 2024, more supply, stagnant demand. Hence the cautious cut backs of solar PV larger than 100 kW, on commercial and industrial roofs, and cut back of others only as required’.
When it was said that there are allegations against him for the attempt to curtail, RE, though his own company RMA Energy provided consultancy service to draft the REDMAP that stated the importance in adding RE to the grid and proposed how much RE should add to the system from 2023 to 2026, Dr. Siyambalapitiya said that the consultancy service was provided to the ADB somewhere in 2022 but not to the government of Sri Lanka or to the CEB.
Yes we proposed what the RE capacity that should be added, and how it is to be added and where, well into the future,” he said.
When he was told that CEB Engineers are alleging that he is behind the planned curtailment as he has an interest in coal generation, Dr. Siyambalapitiya queried what evidence this newspaper has that he has interest in coal generation, and what kind of interest is alleged.
‘I am a 65-year old power system planner by profession, since 1982. My overall objective is to work whenever, wherever I am, to ensure Sri Lanka gets electricity at the lowest economic cost, within the government policy framework, whichever the government is in power. So depending on the world trends, I campaign for Sri Lanka to build/not to build different types of power plants for/against government policy and objectives of least cost.
CEB’s decision to purchase diesel and coal at a higher cost has raised eyebrows amongst its own engineers
As you would see, different types of electricity generation has many features: stability, cost, intermittency, renewable, fossil.It is a balancing act; not an argument of this against that, but all types of power plants, big, small, fossil, renewable working together to serve a reliable power supply at lowest cost, aligning with government policy.”
When asked whether he and his wife have divested of their interest in RMA Energy and have resigned from all operations of this company and have no hand in any management and technical control of RMA after accepting the Chairmanship of the CEB which is conflict of interest, and also whether the company has refused offshore wind power pre-feasibility assessment or any other ongoing project in the country’s power sector since he took over CEB office, Dr. Siyambalapitiya said that he resigned as the Managing Director RMA Energy when he took over office at CEB in September 2024.
A new MD has taken over RMA Energy. The company provides consultancy services to banks, developers, governments worldwide. My wife or I have not divested shares in the company. I have no hand in any operations of the company. The company, in any case, is not a service provider to CEB or the Government or Sri Lanka. Offshore wind power pre-feasibility study was conducted for the World Bank in 2023-2024 which was concluded in 2024. I was the team leader of the Sri Lanka study team. The study was won through a competitive bid in 2023.
After I left the Company, the team leader position was also transferred to the new MD. Certainly there was a concluding seminar on the Off Shore windpower study a few weeks ago, to present the findings. The World Bank requested the Ministry of Energy to decide and invite participants to attend a seminar, in which, who did the study, was disclosed, as it is the policy of the government and the World Bank. The study was concluded well before I joined CEB in 2024.
Finally, I agreed to be CEB Chairman for a limited period and that period has now ended. As soon as the government finds a replacement, I will be leaving office,” he said.